After Action Review Process · Part 4
Complete the notes below. Write ONE WORD ONLY for each answer.
Complete the notes below. Write ONE WORD ONLY for each answer.
After Action Review Process
Background
• A way of evaluating during a project in order to make improvements
• Developed by the 31
Benefits
• Not just for large projects can also be used after:
○ a staff meeting
○ a 32 incident
• Develops better team communication because of the emphasis on 33
What is an After Action Review?
It’s a meeting that:
• concentrates on results and the 34 for them
• encourages participation
• stresses the need to 35 each other
Things to remember when conducting an After Action Review
• Use an external facilitator (so stronger team members cannot dominate)
• To encourage participation, get the group’s thoughts in 36
• Remember to use 37 questions
• Give any recommendations to other team 38
• Make sure you follow up on ideas and provide 39 for employees
• Remember to check the 40 often